Street Construction Update

Three projects are tentatively scheduled for 2017.
The first is a new street construction--Province Terrace, which will be located from Midway Road to Province Link. This is planned to begin on April 24, 2017 and be completed by June 16, 2017

The second project is a compilation of many smaller projects set to begin on June 19, 2017 and be competed by October 27, 2017. Some of the new streets being constructed will be the Silver Birch Estates subdivision streets.
Railroad Street from Abby Ave to Garfield Ave will have some reconstruction taking place during this time. Reconstruction means pulverizing and resurfacing the street.
Small sections of various other streets will also be rehabilitated during this project: Deerfield Ave from 100' south of Geneva Road to the North end, Meadowview Drive from 100' south of Geneva Road to Lucerne Drive, Briarwood Drive from Driftwood Way to Lucerne Drive, Apple Court from the south end to Lucerne Drive, Second Street from Tayco Street to Racine Street, Center Street from the west end to Main Street, Garnet Court from the south end to Valley Road, Emerald Court from the south end to Valley Road, Pearl Street from Emerald Court to Alcan Drive, and Manitowoc Street from Fourth Street to Eleventh Street.  Rehabilitation of a street means mill and overlay work on the street. 

The third project will be the Mill Street Reconstruction, which will wake place south of Main Street to the terminus, and is planned to begin in August 2017 and be completed in September 2017. The terminus Beautification part of the project will then begin in September 2017 and be completed in October 2017.